9. Adımdaki Değişiklikler
Düzenleyen: Jillian Oliver —
Düzenleme onaylandı tarafından Jillian Oliver
- Önce
- Sonra
- Değiştirilmemiş
Adım Satırları
[* red] Connect the box to the turbine control board (Pl1.J6.CT). | |
- | [* black] Couple the flow rate measurement block (Pl1-260) to the casing and connect the two O2 supply pipes and the piezo solenoid valve, then reinsert the assembly into its housing. Put the cone support (Pl1-50) also into place. Put the cone support (Pl1-220) also into place. |
+ | [* black] Couple the flow rate measurement block (Pl1-260) to the casing and connect the two O2 supply pipes and the piezo solenoid valve. |
+ | [* black] Then, reinsert the assembly into its housing. Put the cone support (Pl1-50) into place. Put the additional cone support (Pl1-220) also into place. |